TIP Amendments and Administrative Modifications

Revision Calendars

View the TIP Revision Calendar (2025) (PDF).

A TIP revision is a change that is made between full updates of the TIP.  The TIP is regularly revised to update project information, as well as to add or delete projects.  There are two types of TIP revisions – Amendments and Administrative Modifications.

Amendments

A TIP revision is a change that is made between full updates of the TIP.  The TIP is regularly revised to update project information, as well as to add or delete projects.  There are two types of TIP revisions – Amendments and Administrative Modifications. 

An amendment involves a major change to a project in the TIP.  An amendment to the TIP requires an opportunity for review and comment by the public and is approved by the HRTPO Board.  A TIP request that involves any of the following items must be processed as an amendment: 

  • Addition/deletion of a project.
  • Addition/deletion of a project phase.
  • Major change in design concept, scope, or termini.
  • Major change in project phase initiation date (6 to 12 month delay).
  • Ungrouping of a TIP project to add back into the TIP as an individual project
  • Major change in project cost as determined by the Sliding Scales below:

Highway-FHWA Project/Phase Cost Increase Thresholds for Amendments 

Approved STIP Total Estimate Project 
Cost Estimate

Estimate Increase Requiring 
Amendment

Up to $2,000,000

Greater than 100%

Greater than $2,000,000 to $10,000,000

Greater than 50%

Greater than $10,000,000 to $20,000,000

Greater than 25%

Greater than $20,000,000 to $35,000,000

Greater than 15%

Greater than $35,000,000

Greater than 10%

Transit-FTA Project/Phase Cost Increase Thresholds for Amendments

Approved STIP Total Estimate Project
Cost Estimate

Estimate Increase Requiring
Amendment

Up to $2,000,000

Greater than 100%

Greater than $2,000,000 to $10,000,000

Greater than 50%

Greater than $10,000,000 to $20,000,000

Greater than 25%

Greater than $20,000,000 to $35,000,000

Greater than 15%

Greater than $35,000,000

Greater than 10%

Administrative Modifications

An Administrative Modification (Ad-Mod) involves a minor change to the TIP.  Administrative Modifications will be included as attachments to a standing HRTPO Board agenda note each month to inform Board members of the status of locality/agency TIP projects.  The following are examples of items that may be processed as Administrative Modifications: 

  • Minor changes in project/phase costs (see Sliding Scales on previous page).
  • Adding/transferring/swapping/deleting allocations to a project, including CMAQ and RSTP funds
  • Adding/removing obligations.
  • Splitting or combining individually listed projects with no major change in scope/termini
  • Minor project schedule changes.  Ad-mods with subsequent schedule project delays will be reviewed on a case-by-case basis.
  • Project name/description change with no major change in scope.